LWP Home Menu2023 Sweetheart Alley Sanitary Sewer Replacement Project
Project: Replacing sanitary sewer line from the 1920s
Location: Alley between East 4th and East 5th Streets, from Lincoln Avenue to Washington Avenue (known as "Sweetheart Alley")
Construction hours: 7am-6pm Monday-Friday
Start date: July 27, 2023
Completed: December 22, 2023
Project summary
It's our mission to provide safe, reliable utility service to our customers. Infrastructure maintenance is a critical part of that mission.
The sanitary sewer line beneath Sweetheart Alley was originally installed in the 1920s. The line reached the end of its useful life and was replaced.
This project marked the beginning of a multi-phased replacement of the existing gravity sanitary sewer line from Railroad Avenue to Washington Avenue along Sweetheart Alley.
Project map
View a map of the project here.
Community benefits
This project replaced a sewer line that reached the end of its usable life - ensuring safe, reliable wastewater service to all customers near Sweetheart Alley for decades to come.
Project updates
Pre-Project: Customer Letter
Pre-Project: Reporter-Herald Article (Subscriber Article)
August 1, 2023
August 15, 2023
August 24, 2023
August 31, 2023
September 8, 2023
September 15, 2023
September 22, 2023
October 6, 2023
October 13, 2023
October 20, 2023
October 27, 2023
November 2, 2023
November 9, 2023
November 16, 2023
December 1, 2023
Final Report - December 22, 2023
Questions and concerns?
If you have any questions or concerns about this project, feel free to contact Donald Cecil at Donald.Cecil@cityofloveland.org or 970-381-6379.